Jersey roadworks delay welcomed as residents get a break from disruption

6 hours ago
1 min read

A decision to postpone the final phase of major sewer works on a busy Jersey road has been welcomed by a politician, who says it will give residents and businesses some much-needed relief.


The project, which involves renewing 2km of the sewer network on a key route linking St Helier with the northern parishes, has caused disruption since November 2025.


Infrastructure Minister Jonathan Renouf told a scrutiny panel that the final phase would be delayed to prioritise infrastructure improvements at Maufant, supporting a planned development of 30 affordable homes.


Deputy Hilary Jeune, who oversees scrutiny of infrastructure, described the decision as the right move. She said it would also provide an opportunity for the government to improve communication and ensure future works run more smoothly.


The current second phase is expected to continue until the end of May next year, while work at Maufant could take until 2029 to complete.


Local businesses have previously raised concerns about the impact of the roadworks, with some saying they were struggling due to reduced trade.


Alan Bonny, who has run Bonny's Country Garden with his wife for around 35 years, said the works had made the area quieter, although customers were still managing to reach the business.


Deputy Jeune said better communication would be essential when the project eventually resumes, ensuring residents can access local shops, schools, businesses and essential appointments.


She also raised wider concerns about housing developments being approved without the necessary infrastructure in place, saying this had left the government having to divert resources to address the shortfall.